2023 Construction

It's been a very busy year!

Making Progress!

As of the beginning of 2023 we now have doors and windows installed at Kilolo...

June and July 2023

Electrical Piping

All electrical preparation work was completed as of the summer.

Interior Plumbing

We completed all interior plumbing for Kilolo Christian Heart in June of 2023. Exterior plumbing will be completed in early 2024.

Surround Paving

In August we completed a raised surround for the building; this provides inbuilt seating for the children in the summer as well as protects the foundation from the winter rains.

Cement Plaster Finishing

Through the Fall and by the end of November, all interior walls were plastered and completed.